Schedules and tasks
Add tasks and update their status
Press C anywhere to add a task. Open a task to set its status: Not started, In progress, Blocked or Done. Choosing Blocked asks for a reason, so everyone can see what the job is waiting on.
Add a task
- Press C, or on a phone tap + in the bottom bar.
- Type the task name and, if you like, the dates, who it's assigned to and the phase. More options shows the rest.
- Click Add task. Turn on Add another to keep going.
Statuses
- Not started: scheduled, no work yet.
- In progress: the crew is on it.
- Blocked: waiting on something. Pick a reason (Inspection, Material, Weather, Waiting on a trade, Waiting on a decision or Other), add a note if you like, then click Mark blocked. Moving off Blocked clears the reason.
- Done: finished and checked. Click Mark done in the task.
In the task
Click a task to open it on the side (on a phone it opens full screen). Set Status, % done, Assigned to, the trade partner, Phase, dates and duration, add notes, and see its history.
The … menu has Duplicate, Move to phase…, Convert to milestone, Shift dates… and Archive, which you can undo. A milestone is a moment, not work, like a permit issued. Inspections and deliveries show their own icon.
Field users can add and update tasks on the projects they're on, unless their project role is Can view. Viewers can look but not change anything.
Did this answer your question?
Related articles
- Link tasks so one waits for anotherOpen the later task, click Add link to task (or press L) and pick the task it waits for. By default it starts after that task finishes. When the earlier task slips, the tasks waiting on it are pushed along.
- Why is a task late or at risk?A task is Late when it isn't done and its finish date has passed. It's At risk when it's blocked, has started but is 25 or more points behind where it should be, or its start date has passed and it hasn't started. Days are counted in workdays.
- Schedule views: list, board, calendar, timelineEvery schedule has five layouts: List, Board, Calendar, Timeline (Gantt on commercial projects) and Table. Switch with the layout button above the schedule, or press 1 to 5. Quick views, Filters and Display change what you see, never the schedule itself.