Import a schedule from Excel or MS Project
Upload it as a schedule template: Planning › Schedule templates › New template › Upload a file. It reads CSV or TSV exports from Excel, MS Project or Primavera and shows a preview before you save. Then use it on a new project, or on one whose schedule is still empty.
- Export your schedule as CSV or TSV. Sora Build doesn't open .mpp or .xlsx files directly, so save or export from Excel, MS Project or Primavera first.
- Go to Planning › Schedule templates, click New template and choose Upload a file.
- Choose the file under Schedule file. Give it a Template name and set Used for to Homes or Commercial.
- Check the preview: how many tasks and phases, the total workdays, the trades, and any notes about the file.
- Click Save template.
What it reads
- Columns named Phase, Task, Trade, Duration and Predecessors. Common alternatives work too, like Activity Name, Resource, Days or Depends on.
- Durations in workdays.
- Predecessors as a task ID, the task's number in the list or its name, written MS Project style: 12, 12FS+3 or 7SS-2.
- Up to 1,000 tasks in 60 phases.
Templates keep finish-to-start and start-to-start links. Finish-to-finish and start-to-finish links are read as the closest of those, with a warning, and gaps over 60 days are capped.
Into an existing project
A template fills a schedule that has no tasks yet: open the project's schedule and choose Use a schedule template. You can't add an import to a schedule that already has tasks.
Uploaded templates belong to your company. Only your team can see or use them.
Did this answer your question?
Related articles
- Schedule templatesA schedule template is a reusable set of phases, tasks, trades, durations and links. Pick one when you create a project and every task is laid out from your start date. Find and manage them under Planning › Schedule templates.
- Create a projectClick New project on the Projects page, choose a home or a commercial project, pick a template and start date (or start blank), then name it. Only the name is required. The Office, Admin and Owner roles can create projects.
- Link tasks so one waits for anotherOpen the later task, click Add link to task (or press L) and pick the task it waits for. By default it starts after that task finishes. When the earlier task slips, the tasks waiting on it are pushed along.
Still stuck?
Signed in? Ask our support agent from the ? menu › Ask a question. Or write to us and a person will answer.